China’s second domestically built large cruise ship, Adora Flora City, set out from the Waigaoqiao dock in Shanghai in the early morning of May 16 for a 12-day sea trial.
The vessel, built by China State Shipbuilding Corporation Limited, has entered the last critical stage before delivery.

Adora Flora City sets out on its sea trial. [Photo/sasac.gov.cn]
A technical team of 937 personnel from 12 countries participated in the sea trial, during which they would conduct a total of 149 experimental verifications covering 45 commissioning procedures, focusing on key performance metrics including navigational capability, maneuverability, propulsion, safety systems, power and navigation systems, as well as full-ship vibration and noise. At the same time, they will also verify key indicators such as vibration noise, speed, and energy efficiency design index.
Since undocking on March 20, the vessel has entered the quayside commissioning phase. Functional tests on both main propellers were completed, and 6,621 hull completion certificates were issued. As of now, the project is 97.8 percent complete, with interior outfitting at 92.3 percent and commissioning at 89.8 percent.
The vessel is scheduled for formal delivery on November 6, marking the start of its inaugural season from the Guangzhou Nansha International Cruise Home Port.
(Executive editor: Zuo Shihan)