A view of the Gantsmod-Gashuunsukhait Railway after its T-beams are installed. [Photo/sasac.gov.cn]
The installation of all T-beams — structural beams shaped like the letter T — on the Gantsmod-Gashuunsukhait Railway, the second cross-border railway link between China and Mongolia, was completed recently, laying a solid foundation for subsequent construction work.

A view of the Gantsmod-Gashuunsukhait Railway after its T-beams are installed. [Photo/sasac.gov.cn]
The construction of the Gantsmod-Gashuunsukhait Railway began nearly 70 years after the Erenhot-Zamiin-Uud Railway opened in 1956. It is expected to serve as a new link in infrastructure connectivity between China and Mongolia.
The railway is being jointly built by the two countries under the principle of “unified design, independent construction and integrated commissioning”. It crosses the border at the Gantsmod port in China and the Gashuunsukhait port in Mongolia before connecting to Gashuunsukhait station in Mongolia’s Umnugovi Province.

A view of the T-beam installation site. [Photo/sasac.gov.cn]
Construction of the Gantsmod-Gashuunsukhait Railway began in May 2025. The route is 9.91 kilometers long, including a 6.08-km cross-border bridge section that requires the installation of 760 T-beams. The heaviest individual beam weighs 149.5 metric tons. Handling and installing such heavy structural components calls for a high level of technical expertise, rigorous safety management and precise equipment operation.

A view of the T-beam installation site. [Photo/sasac.gov.cn]
Overall construction of the railway is progressing steadily so far. Ninety-two percent of the construction in the Chinese section and 62 percent in the Mongolian section have already been completed. All substructure and T-beams of the cross-border bridge have been installed. The railway is expected to see all its tracks laid before the end of this year, with 7.78 km of tracks having been installed.

A view of the T-beam installation site. [Photo/sasac.gov.cn]
The Gantsmod-Gashuunsukhait Railway is an important milestone in deepening strategic alignment and practical cooperation between China and Mongolia. Once operational, it is expected to transport 30 million tons of cargo annually, linking the Gantsmod Railway with Mongolia’s southbound railway network. It is expected to expand bilateral trade, improve transport and logistics connectivity, and stimulate economic activity along the route. It will also support the development of cross-border logistics services, industrial parks and border trade facilities in both countries.
The railway is expected to play an important role in deepening China-Mongolia economic cooperation and advancing high-quality cooperation under the Belt and Road Initiative.
(Executive editor: Zuo Shihan)