CHEC’s Largest Overseas Coal-fired Power Plant Project Starts High-altitude Installation

Updated: 2019-03-27

2019032706_副本.png

The boiler steel structure of the largest coal-fired power plant contracted by CHEC overseas is hoisted on March 20. [Photo/sasac.gov.cn]

Hoisting of the power plant containing two units of 660mW installed capacity in Vietnam, contracted by China Huadian Engineering Co., Ltd. (CHEC), started on March 20, marking the beginning of the high-altitude installation work of CHEC's largest overseas coal-fired power plant.

The construction of the plant is the largest power generation project invested in Vietnam by CHEC and its Malaysian partner. It will provide safe, reliable and clean energy for Vietnam and will alleviate the country's power shortages.

The plant, located in the power generation industrial park in Duyên Hải district of Trà Vinh province in Vietnam, will feature two super-critical generator sets of 660mW installed capacity and a supporting coal unloading wharf.

CHEC holds 51 percent of the project's stock and shoulders engineering procurement and construction duties.

The project started on May 26, 2017 and is scheduled for completion in 2021.



(Executive editor: Hao Wen)

Copyright ©  State-owned Assets Supervision and Administration Commission of the State Council All rights reserved. Presented by China Daily